doc: releases: replace merge window terminology
Do not use the merge window terminology which can be confusing and use "development phase" and "stabilisation phase" instead. Signed-off-by: Anas Nashif <anas.nashif@intel.com>
This commit is contained in:
parent
28fa1761c2
commit
c2f1b8db7b
|
@ -14,29 +14,28 @@ the features that have actually been implemented, allowing the project to
|
|||
maintain the quality of the overall release without delays because of one or two
|
||||
features that are not ready yet.
|
||||
|
||||
The Zephyr release model is loosely based on the Linux kernel model:
|
||||
The Zephyr release model was loosely based on the Linux kernel model:
|
||||
|
||||
- Release tagging procedure:
|
||||
|
||||
- linear mode on main branch,
|
||||
- release branches for maintenance after release tagging.
|
||||
- Each release period will consist of a merge window period followed by one or
|
||||
more release candidates on which only stabilization changes, bug fixes, and
|
||||
documentation can be merged in.
|
||||
- Each release period will consist of a development phase followed by a
|
||||
stabilization phase. Release candidates will be tagged during the
|
||||
stabilization phase. During the stabilization phase, only stabilization
|
||||
changes such as bug fixes and documentation will be merged unless granted a
|
||||
special exemption by the Technical Steering Committee.
|
||||
|
||||
- Merge window mode: all changes are accepted (subject to approval from the
|
||||
respective maintainers.)
|
||||
- When the merge window is closed, the release owner lays a vN-rc1 tag and the
|
||||
tree enters the release candidate phase
|
||||
- CI sees the tag, builds and runs tests; QA analyses the report from the
|
||||
build and test run and gives an ACK/NAK to the build
|
||||
- The release owner, with QA and any other needed input, determines if the
|
||||
- Development phase: all changes are accepted (subject to approval from the
|
||||
respective maintainers).
|
||||
- Stabilisation phase: the release manager creates a vN-rc1 tag and the tree
|
||||
enters the stabilization phase
|
||||
- CI sees the tag, builds and runs tests; Test teams analyse the report from the
|
||||
build and test run and give an ACK/NAK to the build
|
||||
- The release owner, with test teams and any other needed input, determines if the
|
||||
release candidate is a go for release
|
||||
- If it is a go for a release, the release owner lays a tag release vN at the
|
||||
same point
|
||||
- Development on new features continues in topic branches. Once features are
|
||||
ready, they are submitted to mainline during the merge window period and after
|
||||
the release is tagged.
|
||||
|
||||
.. figure:: release_cycle.png
|
||||
:align: center
|
||||
|
@ -46,38 +45,41 @@ The Zephyr release model is loosely based on the Linux kernel model:
|
|||
|
||||
Release Cycle
|
||||
|
||||
Merge Window
|
||||
*************
|
||||
Development Phase
|
||||
*****************
|
||||
|
||||
A relatively straightforward discipline is followed with regard to the merging
|
||||
of patches for each release. At the beginning of each development cycle, the
|
||||
"merge window" is said to be open. At that time, code which is deemed to be
|
||||
sufficiently stable (and which is accepted by the development community) is
|
||||
main branch is said to be open for development. At that time, code which is deemed to be
|
||||
sufficiently stable (and which is accepted by the maintainers and the wide community) is
|
||||
merged into the mainline tree. The bulk of changes for a new development cycle
|
||||
(and all of the major changes) will be merged during this time.
|
||||
|
||||
The merge window lasts for approximately two months. At the end of this time,
|
||||
the release owner will declare that the window is closed and release the first
|
||||
The development phase lasts for approximately two months. At the end of this time,
|
||||
the release owner will declare that the development phase is over and releases the first
|
||||
of the release candidates. For the codebase release which is destined to be
|
||||
0.4.0, for example, the release which happens at the end of the merge window
|
||||
will be called 0.4.0-rc1. The -rc1 release is the signal that the time to merge
|
||||
3.1.0, for example, the release which happens at the end of the development phase
|
||||
will be called 3.1.0-rc1. The -rc1 release is the signal that the time to merge
|
||||
new features has passed, and that the time to stabilize the next release of the
|
||||
code base has begun.
|
||||
|
||||
Stabilization Phase
|
||||
*******************
|
||||
|
||||
Over the next weeks, only patches which fix problems should be submitted to the
|
||||
mainline. On occasion, a more significant change will be allowed, but such
|
||||
occasions are rare and require a TSC approval (Change Control Board). As a
|
||||
general rule, if you miss the merge window for a given feature, the best thing
|
||||
to do is to wait for the next development cycle. (An occasional exception is
|
||||
made for drivers for previously unsupported hardware; if they do not touch any
|
||||
other in-tree code, they cannot cause regressions and should be safe to add at
|
||||
any time).
|
||||
general rule, if you miss submitting your code during the development phase for
|
||||
a given feature, the best thing to do is to wait for the next development cycle.
|
||||
(An occasional exception is made for drivers for previously unsupported
|
||||
hardware; if they do not touch any other in-tree code, they cannot cause
|
||||
regressions and should be safe to add at any time).
|
||||
|
||||
As fixes make their way into the mainline, the patch rate will slow over time.
|
||||
The mainline release owner releases new -rc drops once or twice a week; a normal
|
||||
series will get up to somewhere between -rc4 and -rc6 before the code base is
|
||||
considered to be sufficiently stable and the quality metrics have been achieved
|
||||
at which point the final 0.4.x release is made.
|
||||
considered to be sufficiently stable and the release criteria have been achieved
|
||||
at which point the final 3.1.0 release is made.
|
||||
|
||||
At that point, the whole process starts over again.
|
||||
|
||||
|
@ -182,7 +184,7 @@ Extended Stabilisation Period
|
|||
|
||||
Zephyr LTS development cycle differs from regular releases and has an extended
|
||||
stabilization period. Feature freeze of regular releases happens 3-4 weeks
|
||||
before the scheduled release date. The stabilisation period for LTS is extended
|
||||
before the scheduled release date. The stabilization period for LTS is extended
|
||||
by 3 weeks with the feature freeze occurring 6-7 weeks before the anticipated
|
||||
release date. The time between code freeze and release date is extended in this case.
|
||||
|
||||
|
@ -192,7 +194,7 @@ Stable APIs
|
|||
Zephyr LTS provides a stable and long-lived foundation for developing
|
||||
products. To guarantee stability of the APIs and the implementation of such
|
||||
APIs it is required that any release software that makes the core of the OS
|
||||
went through the Zephyr API lifecycle and stabilised over at least 2 releases.
|
||||
went through the Zephyr API lifecycle and stabilized over at least 2 releases.
|
||||
This guarantees that we release many of the highlighted and core features with
|
||||
mature and well-established implementations with stable APIs that are
|
||||
supported during the lifetime of the release LTS.
|
||||
|
|